Speech Delivered At Official MoU Signing Ceremony Between Ikeja Electric And Mojec International Ltd |    Crowd Throngs Ikeja Electric's Medical Outreach |    Planned TCN Upgrade Of Ejigbo And Alimosho Power Transformers |    Ikeja Electric Marks Customer Service Week |    Ikeja Electric, XT Monitor Organises Medical Outreach For Lagos Communities    Customers To Enjoy More Power Supply As IE Upgrades Ogudu Injection Substation |    Ikeja Electric At Sixth Edition Of Power Nigeria Exhibition |    Two Jailed For Vandalizing Ikeja Electric Equipment |    Ikeja Electric Promotes 97 Employees |    NSCDC Arrests Two For Vandalising Ikeja Electric Cable |    Ikeja Electric Restores Power To Lagos Community Following Equipment Vandalism |    Ikeja Electric Moves To Name And Shame Energy Thieves |    Ikeja Electric Introduces Young Engineers' Programme |    We’re still providing meters to customers |    Ikeja Electric Re-Engineers Billing Process; Deploys Technology For Instant Billing |    Ikeja Electric Signs Accion MFB As Collecting Bank |    Ikeja Electric Holds Media Chat With Energy Correspondents |    Ikeja Electric Appeals for Understanding as Rainstorm Damages Installations |    NERC Directive On No Meter, No Payment, For Maximum Demand Customers Only |    Ikeja Electric Launches Whistle-Blowing Platform |    Ikeja Electric Holds Safety Sensitization In Primary Schools To Mark Children's Day |    Vandals Arrested, Remanded In Kirikiri Prisons |    Ikeja Electric Cautions Residents Against Activities Under Power Lines |    Ikeja Electric Adds 15MVA Injection Capacity To Her Network |    Non-Energy Bill Payment Now Available On QuickTeller |    Court Jails Man for Vandalizing IE Assets |    IE Launches USSD Solution to Ease Payments |    More UBA Branches Partner With Ikeja Electric |    Ikeja Electric Commissions Two New Injection Substations |

Ikeja Electric Commissions Two New Injection Substations

Ikeja Electric Commissions Two New Injection Substations

The Shomolu and Akowonjo Business Units of Ikeja Electric have strengthened their networks in a concerted bid to improve power supply to customers. The two Business Units recently commissioned two new Injection Sub-Stations at Abule Taylor (1 x 15MVA) and Olowora (1 X 15MVA).

The Abule Taylor Injection station will relieve the existing overloaded Ekoro 2 X 15MVA Injection Substation while Olowora Injection Sub-Station will relieve the overloaded Ojodu and Isheri Injection Substations which will further strengthen the 11kv feeders supplying Isheri, Omole Phase ll and environs.

IE continues to strengthen our network with significant investment in infrastructure expansion as we strive to provide quality service to our customers at all times.

Newly Commissioned Abule Taylor 1 X 15 MVA