Are You Ready For The Rains? |    Ikeja Electric Inducts 32 Graduates Into Its Young Engineers Programme Scheme |    Ikeja Electric Marks World Day For Safety & Health At Work |    ADB President Advocates Cost Reflective Tariff |    Easter Holiday: Ikeja Electric Assures Customers Of Efficient Service Delivery |    Youth Empowerment: Ikeja Electric Partners Slot Foundation To Train 40 Youth |    Technical Hub Operations Commence In Shomolu Business Unit |    Ikeja Electric Launches Bill Dispute Resolution Panel To Resolve Billing Related Cases |    Ikeja Electric Takes Bold Approach To Customer Service |    E-Billing (Paperless Billing) For MD Customers Goes Live |    24 Cable Jointers Get Training Boost |    Staff Assault: Ikeja Electric Goes Tough On Offenders    Man Remanded In Kirikiri Maximum Prisons For Assaulting Ikeja Electric Staff |    Suspect Who Stabbed IE Staff Arrested, Arraigned, Pleads Guilty |    Press Statement: Rising Spate Of Attacks On Our Staff |    Ikeja Electric Celebrates Valentine's Day With Kids At National Orthopaedic Hospital, Igbobi |    Ikeja Electric's Quality, Health, Safety & Environment Department Holds Safety Village Meeting |    Ikeja Electric's Statement On Viral Video |    Steps On How To Use The i-Safe App |    Handling Cases Of Stolen Prepaid Meters |    Notice Of Planned Outage |    Ikeja Electric Cautions Public Against Activities Around Power Lines |    Ikeja Electric Expands Network For Improved Service Delivery, Commences E-Pole Tagging |    Ikeja Electric Retains Top 100 Slot |    Ikeja Electric's QHSE Department Unveils 2019 Slogan |    Ikeja Electric Introduces Customer Enlightenment Drama Series |    Abimbola Mutiat: Our Sincere Condolences |    Yuletide: Ikeja Electric Expands Network Maintenance to Ensure Stable Supply |    Ikeja Electric Wins SERAS Innovation Prize for 2018 |    Ikeja Electric Targets Zero Fatality, Launches QHSE Academy To Deepen Safety Culture |    Ikeja Electric Bags Corporate Pacesetter HSE Campaign |    Ikeja Electric Rehabilitates Agege Injection Substation |    Ikeja Electric Bags Award For Commitment To Safety |    Ikeja Electric Partners XT Monitor To Provide Medicare For Lagosians     Ikeja Electric Develops Mobile App For Customer Safety     Metering Continues Across Ikeja Electric Network Areas |    We’re Bridging Metering Gap, Reducing Estimated Billing with Meter Roll-Out |    "We Won't Slow Down On Safety Initiatives" - Ikeja Electric |    Ikeja Electric Supports Cleaner Lagos Project |    Ikeja Electric Donates Food Clothes To Mark 2018 International Charity Day |    Lagos Communities Commend Ikeja Electric On Meter Rollout |    Metering Exercise Continues In Earnest As IE Sues For Patience |    Eid-El-Kabir: Ikeja Electric Promises Improved Power Supply |    Ikeja Electric Expands Strategy To Curb Vandalism |    Darkness Looms as NUEE Lays Siege at Ikeja Electric |    Ikeja Electric Parleys With Local Publishers For Outreach To Communities |    Ikeja Electric Promotes 299 Employees, Employs Over 500 New Staff |    3 Remanded in Prison for Stealing Ikeja Electric cables |    IKEJA ELECTRIC Keeps Promise, Unveils Aggressive Metering Plan |    IE PowerPlay Debuts on Google Playstore |    Ikeja Electric Introduces Crowd Management Technology At Service Centers |    More Accolades For Ikeja Electric's Safety Initiatives |    Ikeja Electric Deploys Technology To Reduce Downtime |    Ikeja Electric Moves Against Illegal Reconnection Cartel In Akute, Nabs Kingpin! |    Ikeja Electric Canvasses Dialogue As Akowonjo Holds Customer Fair |    Ogba Area Command Assures Ikeja Electric Of Support |    Ikeja Electric Customers To Enjoy Improved Turnaround Maintenance Services |    Ikeja Electric Reaffirms Support For Education Sector Development |    Ikeja Electric Recruitment Policy Boosts Enrollment Into Technical Colleges |

Ikeja DISCO PLANS TO ALLOCATE 1,320MW TO LAGOS

Ikeja DISCO PLANS TO ALLOCATE 1,320MW TO LAGOS

The Ikeja Electricity Distribution Company (IKEDC) has written to the Nigerian Electricity Regulatory Commission (NERC) to signify its intention to allocate 1,320megawatts expected from the doubling of the current capacity of the Egbin Power Plant to Lagos State.

Speaking at the just-concluded 7th Lagos Economic Summit tagged ‘EHINGBETI 2014,’ the Managing Director of Sahara Power, the new owner of the 1,320 megawatt-capacity Egbin Power Station and the Ikeja Electricity Distribution Company, Mr. Kola Adesina said when the new investors took over Egbin plant and IKEDC in November 2013, they realised that they could not wait for the long years stipulated in the privatisation documents for them to increase the capacities of the assets.

Adesina stated that if the investors would wait for the number of years provided in the privatisation documents before increasing the capacities of the assets they acquired, it would be difficult for a reliable power supply to be achieved.

He noted that the encounter the new investors had with the Lagos State Government showed that state government urgently required 10,000megawatts of electricity to industrialise the state and improve the quality of life of the people.

Adesina disclosed that Egbin has a capacity to generate 1,320megawatts but the Power Purchase Agreement (PPA) the new buyers signed with the Nigerian Bulk Electricity Trading Company indicated only 1,100megawatts.
“So, the first thing we did was to say that the 220megawatts capacity that was not captured in the PPA will be dedicated to Lagos State alone. Additionally, the initial commitment we had with the Bureau of Public Enterprises (BPE) was that we were going to generate additional capacity of 1,350megawatts from Egbin,” he said.

He said the company had written to NERC to notify it of its intention to double the capacity at Egbin, and also informing the regulator that the additional capacity would be domiciled to Lagos. Adesina noted that while the new investors have laudable ambition since they took over the assets, shortage of gas has remained a major challenge.

“People do not know the peculiarity of the power infrastructure and that there exists a value chain. People do not know that the man that distributes electricity will have nothing to distribute if there is no gas. So, the very first thing that requires urgent attention is for us to get the gas readily available for us to be able to transmit and distribute the capacity that is desirable,” he added.

The Sahara Power boss stated that Ikeja Electricity Distribution Company disco has a capacity to distribute 950megawatts of electricity but received a maximum of 650megawatts for only two days since the past seven years.

“Since we took over, the highest capacity that has been deployed by the Transmission Company to Ikeja Disco was 407megawatts. If you do not have power to distribute, you cannot distribute power. It is what is given to you that you take. At one point on a Sunday we were able to get only 118megawatts from the system,” he said.
He said Ikeja Disco and Eko Disco were supposed to receive 15per cent and 11per cent, respectively, of the available power capacity in the system but shortage of gas has made it impossible for the two companies to receive these allocations.

Credit: ThisDay Newspaper